菲迪克红皮书翻译英文(雇主篇)——FIDIC红皮书翻译

1.  雇主
THE EMPLOYER

1.1  进入现场的权利
1.1 Right of Access to the Site

雇主应在投标函附录中注明的时间(或各时间段)内给予承包商进入和占用现场所有部分的权利。此类进入和占用权可不为承包商独享。如果合同要求雇主赋予(承包商)对基础、结构、永久设备或通行手段的占用权,则雇主应在规范注明的时间内按照规范中规定的方式履行该职责。但是在收到履约保证之前,雇主可以不给予任何此类权利或占用。

The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time (or times) stated in the Appendix to Tender. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received.

如果投标函附录中未注明时间,则雇主应在一合理的时间内给予承包商进入现场和占用现场的权利,此时间应能使承包商可以按照第8.3款【进度计划】提交的进度计划顺利开始施工。

If no such time is stated in the Appendix toTender, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted under Sub-Clause 8.3 [Programme].

如果由于雇主一方未能在规定时间内给予承包商进入现场和占用现场的权利,致使承包商延误了工期和(或)增加了费用,承包商应向工程师发出通知,并依据第20.1款【承包商的索赔】有权:

If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:

(a) 如果竣工已经或将被延误,根据第8.4款【竣工时间的延长】的规定,对所有此类延误获得延长的工期,以及

(a) an extension of time for any such, delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) 获得任何有关费用加上合理利润的支付,并将之加入合同价格。

(b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

在收到此通知后,工程师应按照第3.5款【决定】对此事作出商定或决定。

After receiving this notice, the Engineer shall proceed in accordance with Sub Clause 3.5 [Determinations] to agree or determine these matters.

然而,如果雇主的过失(并且在一定程度上)是由于承包商的某些错误或延误造成的,包括承包商的文件中的错误或提交的延误,则承包商无权要求获得此类延长的工期、费用或利润。

However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's documents, the Contractor shall not be entitled to such extension of time, Costor profit.

1.2  许可、执照和批准
2.2 Permits, Licences or Approval

雇主应根据承包商的请求,为以下事宜向承包商提供合理的协助(如果他的地位能够做到),以帮助承包商:

The Employer shall (where he is in a position to do so) provide reasonable assistance to the Contractor at the request of the Contractor:

(a) 获得与合同有关的但不易取得的工程所在国的法律的副本,以及

(a) by obtaining copies of the Laws of the Country which are relevant to the Contract but are not readily available, and

(b) 申请法律所要求的许可、执照或批准,包括

(b) for the Contractor's applications for any permits, licences or approvals required by the Laws of the Country:

(i) 依据第1.13款【遵守法律】要求承包商必须获得的,

(i) which the Contractor is required to obtain under Sub-Clause 1.13 [Compliance with Laws],

(ii) 为了货物的运送,包括清关所需的,以及

(ii) for the delivery of Goods, including clearance through customs, and

(iii) 当承包商的设备运离现场而出口时所需的。

(iii) for the export of Contractor's Equipment when it is removed from the

1.3  雇主的人员
2.3 Employer's Personnel

雇主有责任保证现场的雇主的人员和雇主的其他承包商:

The Employer shall be responsible for ensuring that the Employer's Personnel and the Employer's other contractors on the Site:

(a) 依照第4.6款【合作】为承包商的工作提供合作,以及

(a) co-operate with the Contractor's effort sunder Sub-Clause 4.6 [Co-operation], and

(b) 采取类似于承包商按照第4.8款【安全措施】(a)、(b)和(c)段和第4.18款【环境保护】的要求而应采取的措施。

(b) take actions similar to those which the Contractor is required to take under sub paragraphs (a), (b) and (c) of Sub-Clause 4.8 [Safety Procedures] and under Sub-Clause 4.18 [Protection of the Environment].

1.4  雇主的资金安排
2.4 Employer's Financial Arrangements

在接到承包商的请求后,雇主应在28天内提供合理的证据,表明他已作出了资金安排,并将一直坚持实施这种安排,此安排能够使雇主按照第14条【合同价格和支付】的规定支付合同价格(按照当时的估算值)的款额。如果雇主欲对其资金安排做出任何实质性变更,雇主应向承包商发出通知并提供详细资料。

The Employer shall submit. within 28 days after receiving any request from the Contractor, reasonable evidence that financial arrangements have been made and are being maintained which will enable the Employer to pay the Contract Price (as estimated at that time) in accordance with Clause 14 [Contract Price and Payment]. If the Employer intends to make any material change to his financial arrangements, the Employer shall give notice to the Contractor with detailed particulars.

1.5  雇主的索赔
2.5 Employer's Claims

如果雇主认为按照任何合同条件或其它与合同有关的条款规定他有权获得支付和(或)缺陷通知期的延长,则雇主或工程师应向承包商发出通知并说明细节。但对于按照第4.19款【电、水、气】、第4.20款【雇主的设备及免费提供的材料】的规定,承包商应支付的款额或其它因承包商要求某些服务而应支付的款额,则无须发出通知。

If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer shall give notice and particulars to the Contractor. However, notice is not required for payments due under Sub-Clause 4.19 [Electricity, Water and Gas], under Sub-Clause 4.20 [Employer's Equipmentand Free-Issue Material], or

当雇主意识到某事件或情况可能导致索赔时应尽快地发出通知。涉及任何延期的通知应在相关缺陷通知期期满前发出。

The notice shall be given as soon as practicable after the Employer became aware of the event or circumstances giving rise to the claim. A notice relating to any extension of the Defects Notification Period shall be given before the expiry of such

在细节中应详细说明索赔条款或其它依据,包括雇主按照合同认为他自己有权获得的费用和(或)延期的证明,工程师应依据第3.5款【决定】作出商定或决定:(i) 雇主有权获得的由承包商支付的款额(如有时),以及/或 (ii) 依据第11.3款【缺陷通知期的延长】给予缺陷通知期的延长(如有时)。

The particulars shall specify the Clause or other basis of the claim, and shall include substantiation of the amount and/or extension to which the Employer consider: himself to be entitled in connection with the Contract. The Engineer shall then proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the amount (if any) which the Employer is entitled to be paid by the Contractor, and/or(ii) the extension (if any) of the Defects Notification Period in accordance with SubClause 11.3 [Extension of Defects Notification Period].

此笔款额应在合同价格及支付证书中扣除。雇主仅有权从支付证书中确定的款额中抵消或扣除,或依据本款向承包商另外提出索赔。

This amount may be included as a deduction in the Contract Price and Payment Certificates. The Employer shall only been titled to set off against or make any deduction from an amount certified in a Payment Certificate, or to otherwise claim against the Contractor, in accordance with this Sub-Clause.


 

阅读这篇文章人的还阅读了以下文章

 

相关问答

  • 问:是否需要告知译文的具体用途?
    答:非常有必要。演讲稿不同于网站文章,销售手册不同于产品目录,图表标题不同于道路指示牌,小报文章也不同于企业首次公开募股时用的招股说明书。文章出现的场合和目的不同,则其文体风格、韵律格调、遣词造句和句子长短等等都会不同。经验丰富的译者很可能会问到这些信息,您自己务必要清楚这些内容。与翻译公司建立起长期稳定的合作关系可获得最佳的翻译效果。与他们合作的时间越长,他们就越能理解您的经营理念、战略和产品,译文的质量也就越好。请务必将译文的用途告知客户经理,这样译文才能在最大程度上适应特定的受众和媒介。 尤其是一些证件,如果能告知具体用于,或者交给哪些单位使用,则我们会根据相应的单位盖章,提交资质,这对客户有好处。
  • 问:翻译后会盖章吗?他们要求翻译公司盖章
    答:会的,还会附上营业执照,翻译资格证,盖翻译专用章,骑缝盖章
  • 问:你们的译员都有什么样的背景?
    答:366翻译拥有全国最专业的翻译团队。众所周知译员从业背景很重要,外语好只是基本功。366专职译员有两类: 1、外语专业毕业,有律师、项目管理、外贸和外语培训等从业背景,熟悉相关领域知识; 2、专业技术出身,英语好,有工程师、会计、律师。366翻译安排最合适的人给您提供最专业翻译服务。
  • 问:顾客的文件信息会不会受泄露?
    答:现在是数据大爆炸的时代,稍不注意私人信息就会被泄露,我公司很早就注意到了这个问题,我们采取的办法是签署保密协议,并且顾客的资料在翻译完毕后立即删除